The investment project in Mussalo bulk terminal is progressing
The investment project to increase terminal capacity and increase efficiency in Mussalo bulk terminal is progressing according to plan.
The new wagon unloading station will be finished in August 2020. The new station will increase the wagon unloading capacity with 1-1,5 million tons per year. By summer, Rauanheimo will have invested over 17 million euros in warehouses and equipment.
In order to reach efficient handling of railroad wagons, we have together with the Port of HaminaKotka invested in an additional, separate track for full and empty wagons. The additional track will allow VR to deliver 22 wagons at a time.